V2 - VAV - Induced Heating
This workflow will test a VAV box for its heating operation.
First, we display the initial conditions of the equipment.
Then KODE performs precondition checks to ensure the equipment is ready to be tested
Next we will lower the setpoint to stop heating.
Finally we will raise the setpoint to start heating.
Outcome 🎯 |
This test will check a VAV box's ability to deliver heat when its setpoint is raised. |
Recommended Schedule 📅 |
Run weekly per floor Run when there are comfort complaints in a space or floor. Run when new VAV boxes are installed and programmed.
|
Device | Point Requirements 📌 |
VAV | Occupied Mode |
Discharge Air Temperature |
Zone Temperature |
Zone Temperature Setpoint |
Zone Temperature Setpoint |
AHU | Discharge Air Pressure |
Required Preconditions |
1. | AHU Pressure > Min Pressure Threshold |
*Variations
There is a variant of this workflow which works with occupied heating and cooling setpoints.
There is a variant of this workflow which works with network setpoint.
Workflow Overview
| Test Step | Workflow |
1 | Pre-condition Check | VAV is Occupied AHU Pressure > Min Pressure Threshold
|
2 | Stop Heating | Control: Lower VAV Zone Temp Setpoint Success: VAV DAT near AHU DAT or VAV Zone Temp
|
3 | Start Heating | Control: Raise VAV Zone Temp Setpoint Success: VAV DAT greater than AHU DAT
|

Successful Test Example
Failed Test Example
Tuning Parameters
| Test Step | Result Description |
1 | AHU Min Pressure | If AHU Pressure is less than this number, the test automatically archives |
2 | VAV Zone Temp Setpoint Adjustment | How far below zone temp should the setpoint be set to stop heating? How far above zone temp should the setpoint be set to start heating? |
3 | VAV Stop Heating | After lowering the VAV setpoint, the VAV DAT should approach the zone temperature. How close does the VAV DAT need to be to verify that heating has stopped? |
4 | AHU Stop Heating | After lowering the VAV setpoint, the VAV DAT should approach the AHU DAT. How close does the VAV DAT need to be to verify that heating has stopped? |
5
| AHU Start Heating Temp
| After raising the VAV setpoint, the VAV DAT should rise above the AHU DAT. How much greater should the VAV DAT be than AHU DAT to verify that heating has started? |
6 | Max Sequence Duration | What is the maximum length of time in seconds that a sequence should take to execute? |
7 | Min Sequence Duration | What is the minimum length of time in seconds that a sequence should take to execute? |
8 | Stabilization Time | How long in seconds should the program wait when one sequence finishes, before moving onto the next? |
If you need assistance with interpreting your results, reach out to the support team at [email protected].
Related Articles
VAV - Heating Operation
Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the VAV is in operation. Verify that VAV is “Occupied”. Verify that it’s parent AHU is “Occupied Verify fan is running by checking that duct pressure is more ...
VAV/FCU - Induce Heating & Check for Feedback
Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the unit is in operation. Verify that device is “Occupied”. If this condition is not met, STOP the workflow and ARCHIVE. Test the Fan Test 1: Stop the Fan ...
VAV/FCU - Induce Heating/Cooling & Check for Feedback
Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the unit is in operation. Verify that device is “Occupied”. If this condition is not met, STOP the workflow and ARCHIVE. Test the Fan Test 1: Stop the Fan ...
HP - Heating/Cooling Operation
Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the FCU is running. Verify that device is “Occupied”. If this condition is not met, STOP the workflow and ARCHIVE. Setup Testing Conditions In order to ensure ...
FTT PROJECTS USER GUIDE
Hello there ? If you’re reading this, then you’re well on your way to functionally testing your building. To get started, enter the main FTT page from the left sidebar on KODE OS. In the 3 dots, you will see projects. FTT Projects are a new concept ...