Testing Procedure

Pre-Conditions Check

Before testing is started, it must be verified that the AHU is running.
  • Verify that device is “Occupied”.
  • Verify fan is running by checking that duct pressure is more than 0.4psi [Pressure Min Threshold]
If any of these conditions are not met, STOP the workflow and ARCHIVE.

Setup Testing Conditions

In order to ensure that testing is accurate, outside air temperature must be high enough to prevent freezing of the damper if it were to close.
  • Verify that outside temperature is greater than 35°F [OAT Full Ventilation] .

Test Damper Operation

Open Mixed Damper
  • Command mixed damper to “OPEN”
  • Pass if mixed air achieves a temperature greater than 5△°F [Full Mix - Delta] below return temperature
Close Mixed Damper
  • Command mixed damper to “CLOSED”
  • Pass if if mixed air achieves a temperature less than 5△°F [Ventilation - Delta] above outside temperature


Tuning Parameters

DisplayHint
Pressure Min Threshold [0.4psi] How much should the duct pressure be minimally.
OAT Full Ventilation [35°F] The OAT minimum setpoint to allow full ventilation.
Full Mix - Delta [5△°F] The temperature threshold tolerance for fully open mixed damper. Delta below RAT for fully open mixed damper.
Ventilation - Delta [5△°F] The temperature threshold tolerance for fully open mixed damper. Delta below RAT for fully open mixed damper.
Reaction Time [300sec] How long to wait for the actuators to fully do their job.
Stabilization Time [60sec] How long to wait for the system to come to stability after we have given it an actuator command and the conditions have been fullfiled.
Measure After [60sec] How long to wait in seconds to start checking the feedback readings.

    • Related Articles

    • AHU - VFD Operation

      Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the AHU is running. Verify that device is “Occupied”. Verify fan is running by checking that duct pressure is more than 0.4psi [Pressure Min Threshold] If this ...
    • VAV - Damper Operation

      Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the VAV is in operation. Verify that VAV is “Occupied”. Verify that it’s parent AHU is “Occupied Verify fan is running by checking that duct pressure is more ...
    • FTT Projects

      Hello there ? If you’re reading this then you’re well on your way to functionally testing your building. To get started, enter the main FTT page from the left sidebar on KODE OS. In the 3 dots, you will see projects. The idea is to create a ...
    • VAV - Heating Operation

      Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the VAV is in operation. Verify that VAV is “Occupied”. Verify that it’s parent AHU is “Occupied Verify fan is running by checking that duct pressure is more ...
    • FCU - Fan Operation

      Testing Procedure Pre-Conditions Check Before testing is started, it must be verified that the FCU is running. Verify that device is “Occupied”. If this condition is not met, STOP the workflow and ARCHIVE. Setup Testing Conditions In order to ensure ...